ConstructionCalculators

Concrete Calculator

Cubic yards, bags and cost for a slab, footing, pier, wall, steps or curb.

Width 10 ftLength 10 ft4 in
Dimensions
ft
ft
in

You need

1.36cu yd

36.7 cu ft · 1.04 m³ · includes 10% extra

4,960 lb to haul
62
Cost by truck
$348
Cost in bags
$403
Concrete weightat 150 lb per cu ft
5,000 lb

How Much Concrete Do I Need?

A 10 × 10 ft slab 4 inches thick takes 1.23 cubic yards of concrete. With 10% extra for waste, order 1.36 cubic yards, or buy 62 bags of 80 lb mix.

Common jobs, with 10% extra included:

ProjectSizecu ydBags
AC or equipment pad3 × 4 ft, 4 in0.168
Shed pad8 × 10 ft, 4 in1.0949
Patio10 × 10 ft, 4 in1.3662
Hot tub pad8 × 8 ft, 6 in1.3059
Sidewalk4 × 30 ft, 4 in1.6374
Patio12 × 12 ft, 4 in1.9688
Two-car garage floor24 × 24 ft, 4 in7.82352
Driveway12 × 40 ft, 5 in8.15367

Mixing by hand, one person turns out about a cubic yard an hour, and the U.S. Army's concrete manual treats hand mixing as uneconomical above about one cubic yard. That is roughly where a ready-mix truck starts to make sense.

Concrete for Common Slab Sizes

Cubic yards to order for a rectangular slab, with 10% extra:

Slab4 in5 in6 in
4 × 4 ft0.220.270.33
8 × 8 ft0.871.091.30
10 × 10 ft1.361.702.04
10 × 12 ft1.632.042.44
12 × 12 ft1.962.442.93
12 × 20 ft3.264.074.89
16 × 16 ft3.484.355.21
20 × 20 ft5.436.798.15
24 × 24 ft7.829.7811.73
30 × 30 ft12.2215.2818.33
30 × 40 ft16.3020.3724.44

A 4 × 4 ft pad 4 inches thick is a job for 10 bags of 80 lb mix. A 30 × 40 ft slab at the same thickness takes 16.30 cubic yards, more than one truck carries.

How Many Bags of Concrete Do I Need?

Divide the volume in cubic feet by what one bag makes. An 80 lb bag of premixed concrete yields about 0.60 cubic feet, so one cubic yard (27 cu ft) takes 45 bags.

Bag sizeYield per bagBags per cubic yard
40 lb0.30 cu ft90
50 lb0.38 cu ft72
60 lb0.45 cu ft60
80 lb0.60 cu ft45
90 lb0.66 cu ft41

Yields differ slightly between products. One maker's 60 lb bag of 5,000 psi mix yields 0.47 cu ft instead of 0.45.

One maker ships 80 lb bags 42 to a pallet, 60 lb bags 56 and 40 lb bags 80. A pallet of 80 or 60 lb bags makes about 25 cubic feet, just under a cubic yard, and weighs 3,360 lb. For fence and deck posts, count the bags for each post hole after taking out the post.

3 ft3 ft3 ft
1 cubic yard3 × 3 × 3 ft = 27 cu ft= 45 bags of 80 lb mix= 60 bags of 60 lb mix= 90 bags of 40 lb mix1 cu ft

Why Some Calculators Say 51 Bags per Yard

They count bags by weight: a cubic yard of concrete weighs about 4,050 lb, and 4,050 ÷ 80 = 50.6, rounded up to 51. That method leaves out the water you add to each bag, so it gives a few more bags than you actually need. It works as a built-in safety margin.

This calculator counts by bag yield by default. To use the weight method, set Count bags by to Weight.

Number of 80 lb bags by slab size, with 10% extra:

4 in slab6 in slab
10 × 10 ft
62
92
12 × 12 ft
88
132
16 × 16 ft
157
235
20 × 20 ft
245
367
4 in slab, 6 in slab, in 80 lb bags

How to Measure for Concrete

  1. 1Measure the length and width in feet, inside the forms. Forms built from 2×4 lumber are 3½ inches deep, not 4.
  2. 2Measure the depth in inches in several spots and use the average. On a 4 in slab, just 1/8 inch of extra depth leaves your order about 3% short.
  3. 3Split odd shapes into rectangles and circles, work out each one and add them. In the calculator, use Add another slab for each part.
  4. 4For round piers and sonotubes, measure the inside diameter and the depth of the hole.
  5. 5Add extra for waste. The calculator adds 10% by default. The American Concrete Institute suggests 10 to 15% on small loads and 5 to 10% on large ones.
10 ft12 ft6 ft6 ftAB
A = 10 × 12 ftB = 6 × 6 ft4 in thick

For the L-shaped patio above: 120 sq ft + 36 sq ft = 156 sq ft. At 4 inches that is 52 cubic feet, or 1.93 cubic yards. With 10% extra, order 2.12 cubic yards, or 96 bags of 80 lb mix.

Why Concrete Comes Up Short

Ready-mix is sold by the volume of fresh concrete that leaves the truck, not by the size of your forms. When a pour runs short, the cause is usually on site:

  • A slab thicker than planned. The 1/8 inch that leaves a 4 in slab 3% short is a whole cubic yard on a 32-yard pour.
  • Forms that bow out under the weight of the wet concrete.
  • A low or uneven base, loose fill that settles during the pour, and spots dug too deep.
  • Spills, and concrete used along the way for small extras such as a post footing.

Hardened concrete also takes up about 2% less space than it did fresh. On a pour of several trucks, measure what is left to fill toward the end and tell the plant before it loads the last two or three.

How to Calculate Concrete Volume

Multiply length by width by thickness, with all three in feet, then divide by 27 to get cubic yards:

Cubic yards = L (ft) × W (ft) × T (in) ÷ 12 ÷ 2710 × 10 × 4 ÷ 12 = 33.33 cu ft33.33 ÷ 27 = 1.23 cu yd1.23 × 1.10 extra = 1.36 cu yd to order
  • SlabV = L × W × T
  • FootingV = L × W × D
  • Pier / ColumnV = π × r² × H
  • WallV = L × H × T
  • StepsV = W × D × R × n(n+1)/2
  • Curb & GutterV = L × (curb + gutter area)
All sizes in feet · cu ft ÷ 27 = cu yd

Other shapes use the same idea: find the volume in cubic feet, then divide by 27.

  • Footing: length × width × depth. A continuous footing 1 ft 4 in wide and 10 in deep is a long, narrow slab. You can also size pads and stepped footings.
  • Pier, column or sonotube: π × radius² × height, with the radius equal to half the diameter. A 12 in sonotube filled 4 ft deep holds 3.14 cubic feet, which is 6 bags of 80 lb mix. For many piers at once, calculate the cylinders together.
  • Round slab: π × radius² × thickness. An 8 ft round pad 4 in thick holds 16.8 cubic feet (0.62 cubic yards). In the calculator, choose Pier / Column and enter 8 ft as the diameter and 4 in as the height.
  • Triangle: ½ × base × height × thickness. A triangle with a 10 ft base and an 8 ft height has the area of a 10 × 4 ft rectangle, so enter it as that slab.
  • Wall: length × height × thickness.
  • Steps: width × tread depth × riser height × n(n + 1) ÷ 2, where n is the number of steps. This treats the steps as solid concrete on the ground. Three steps 4 ft wide with 7 in risers and 11 in treads come to 12.8 cubic feet (0.48 cubic yards) before extra.
  • Curb and gutter: length × the area of the cross-section (curb plus gutter).

Square Feet per Cubic Yard

At 4 inches, a cubic yard covers 81 square feet, so square feet ÷ 81 gives cubic yards before the extra. At other thicknesses:

ThicknessSq ft / cu ydcu yd / 100 sq ft
3½ in92.61.08
4 in81.01.23
5 in64.81.54
6 in54.01.85
8 in40.52.47
12 in27.03.70

Slab With a Thickened Edge

Garage and shed slabs are often poured in one piece with a deeper edge that does the job of a footing, called a monolithic or turned-down slab. Count it in two parts: the whole slab at its normal thickness, plus the part of the edge that goes below the slab.

For a 24 × 24 ft slab 4 inches thick with an edge 12 inches wide and 12 inches deep:

Edge = length around × edge width × (edge depth − slab thickness)Slab: 24 × 24 ft × 4 in = 192 cu ftEdge: 92 ft × 1 ft × 8 in = 61.3 cu ft253.3 cu ft ÷ 27 = 9.38 cu yd, 10.32 with 10% extra
12 in12 in4 in123
  1. 1Slab, 24 × 24 ft and 4 in thick
  2. 2Edge below the slab: 92 ft long, 12 in wide, 8 in deep
  3. 3Gravel base

Measure the edge along its middle, 4 × 24 ft − 4 × 1 ft = 92 ft, so the corners aren't counted twice. In the calculator, enter the slab, press Add another slab, switch the new part to Footing and enter 92 ft by 12 in by 8 in. A truck order rounds up to 10.5 cubic yards, about $1,733 at $165 a yard.

How wide and deep the edge has to be depends on the frost depth, the soil and local code; check the footing size against them. To count the bars in the slab and the edge, use the rebar calculator.

Concrete Steps With a Landing

Front steps usually end at a landing by the door. Count the landing as a block as tall as all the risers together, then add the steps in front of it.

For steps 4 ft wide with three 7 in risers, the landing is 21 inches high. With a landing 4 ft deep, two steps with 11 in treads stand in front of it:

Landing = width × depth × total heightLanding: 4 × 4 ft × 21 in = 28 cu ftSteps: 4 ft × 11 in × 7 in × (2 × 3 ÷ 2) = 6.4 cu ft34.4 cu ft ÷ 27 = 1.27 cu yd, 1.40 with 10% extra
4 ft21 in7 in11 in12
  1. 1Landing 4 ft wide, 4 ft deep and 21 in high
  2. 2Two steps 4 ft wide: 7 in rise, 11 in tread

That is 64 bags of 80 lb mix. In the calculator, choose Steps: 4 ft wide, 7 in rise, 11 in tread, 2 steps. Then add a second part, switch it to Slab and enter the landing, 4 × 4 ft and 21 in thick.

The IRC asks for a landing outside an exterior door at least as wide as the door and 36 inches deep (R311.3), risers no taller than 7¾ inches and treads at least 10 inches deep (R311.7.5).

Ready-Mix Truck or Bags?

In 2026, ready-mix runs about $125 to $195 per cubic yard delivered, with $165 a typical middle figure. Orders below the plant's minimum, often 4 to 5 yards, add a short-load fee, usually $50 to $150. An 80 lb bag costs about $5 to $8, which works out to $225 to $360 per cubic yard in bags.

The calculator starts with $165 per cubic yard plus a $100 short-load fee, and $6.50 per bag. For the default slab that comes to $348 by truck (1.5 cubic yards plus the fee) against $403 in bags.

What decides it besides price:

  • Labor. The default slab is 62 bags of 80 lb mix: 4,960 lb to load, haul and mix. By hand, one person mixes about a cubic yard an hour.
  • One pour. Bags mixed one or two at a time suit posts, pads, steps and small patios. A slab you can't finish in one session ends up with cold joints, where fresh concrete meets concrete that has already started to set.
  • Ordering. Ready-mix is ordered in quarter- or half-yard steps, and one truck carries 8 to 12 cubic yards.

For the full installed price (forms, gravel base, rebar and labor), price the whole concrete job.

How Thick Should a Concrete Slab Be?

Four inches is the standard for patios, walkways and shed pads, and most residential driveways are poured 4 to 5 inches thick. Go to 5 or 6 inches where pickups, RVs or delivery trucks will park. Codes set minimums, not targets: the IRC minimum for a house floor slab is 3½ inches.

ProjectCommon practiceCode or standard
Walkway or patio4 in—
Shed pad4 in—
Hot tub pad4–6 inSpa maker's spec
Two-post car lift, 10,000 lb4¼ in or more, reinforcedLift maker's manual
Driveway for cars4–5 inLocal code
Driveway for pickups, RVs, trucks5–6 inLocal code
Garage floor4 in, 5–6 in for heavy useIRC R506.1: 3½ in minimum
House floor slab4 inIRC R506.1: 3½ in minimum
Footing8–12 in thickIRC R403.1.1: 6 in thick, 12 in wide minimum
Gravel base4–6 in, compactedIRC R506.2.2: 4 in under below-grade floors
Patio / driveway in the UK100 mm / 150 mm—

A car lift's manual sets the floor it needs. One 10,000 lb two-post lift asks for at least 4¼ inches of reinforced 3,000 psi concrete, with the anchors at least 5 11/16 inches from any edge or joint. Where the floor falls short, the same manual calls for a 4 × 4 ft pad 6 inches thick under each post: two pads take 30 bags of 80 lb mix with extra.

Forms built from 2×4 lumber give a slab 3½ inches thick, the IRC floor minimum. Under floor slabs, the IRC also requires a 10-mil vapor retarder; driveways, walks and patios are exempt (R506.2.3). Work out the gravel base under the slab.

wire mesh or rebar4 in concrete4 in gravel basecompacted subgrade

Have a fixed number of bags? Work it backward: thickness in inches = bags × yield ÷ area in square feet × 12. For example, 20 bags of 80 lb mix make 12 cubic feet, enough for a 6 × 6 ft pad 4 inches thick.

How Much Does Concrete Weigh?

Normal-weight concrete weighs 140 to 150 lb per cubic foot, so one cubic yard weighs about 3,780 to 4,050 lb, roughly two tons. In metric, that is 2,240 to 2,400 kg per cubic meter.

The default 10 × 10 ft slab, 4 inches thick, weighs about 4,700 to 5,000 lb. The 62 bags you'd buy for it weigh 4,960 lb, so check your vehicle's payload before you load them all in one trip.

Concrete in Cubic Meters

In metric, multiply length by width by thickness, all in meters. A 3 × 3 m slab 10 cm thick is 0.9 m³; with 10% extra, order 0.99 m³. Switch the calculator to Metric to enter meters and centimeters. One cubic yard is 0.765 m³.

A cubic meter covers 10 m² at 100 mm, 8 m² at 125 mm and 6.7 m² at 150 mm.

Premixed concrete makes about 0.47 liters per kilogram of dry mix: an 80 lb (36.3 kg) bag makes 17 liters. Bags per cubic meter, before extra:

BagMakesBags per m³
20 kg9.4 L107
25 kg11.7 L86
30 kg14.0 L72
80 lb (36.3 kg)17 L59

In Metric, the calculator counts 20, 25 or 30 kg bags at this yield. Check the yield printed on the bag; it varies a little between products.

Cement vs. Concrete and Mix Ratios

Cement is one ingredient of concrete. Concrete is cement, sand, gravel and water. When people search for a cement calculator, they almost always mean concrete.

Premixed bags already contain the cement, sand and gravel, so you add only water. If you mix from scratch, the classic field recipe is 1 part portland cement, 2 parts sand and 3 parts gravel by volume, with just enough water for a workable mix. A 94 lb sack of portland cement is about 1 cubic foot.

Ready-mixed concrete for floors carries at least 470 to 610 lb of cement per cubic yard, depending on the size of the stone (ACI 301 minimums). Brick and block joints take mortar, not concrete, and a thin topping over an existing floor takes a self-leveling underlayment.

Standard bagged concrete mix reaches about 2,500 psi at 7 days and 4,000 psi at 28 days, and 5,000 psi mixes are sold too. The IRC minimum for garage floors, porches and outdoor steps is 2,500 to 3,500 psi depending on the climate, and where winters are moderate or severe it wants that concrete air-entrained too (Table R402.2). Ready-mix is ordered by strength and air content, so tell the plant what the concrete is for.

Frequently Asked Questions

How many 80 lb bags of concrete make a yard?

45 bags. Each 80 lb bag makes about 0.60 cubic feet, and a cubic yard is 27 cubic feet. With 60 lb bags it takes 60, with 40 lb bags 90. Add 10% extra on top.

How much concrete do I need for a 10 × 10 slab?

At 4 inches thick, 1.23 cubic yards; order 1.36 with 10% extra, or 62 bags of 80 lb mix. At 6 inches, 1.85 cubic yards; order 2.04 with extra, or 92 bags.

How many square feet does a yard of concrete cover?

81 square feet at 4 inches thick, 65 at 5 inches and 54 at 6 inches. At 3.5 inches it covers about 93 square feet.

How much extra concrete should I order?

The American Concrete Institute suggests 10 to 15% extra on small loads and 5 to 10% on large ones; the ready-mix industry's own guidance is 4 to 10%. Running short in the middle of a pour is worse than a little left over. The calculator adds 10% by default; change it in Extra for waste.

Is it cheaper to use bags or a ready-mix truck?

It depends on the size of the job. Bags cost more per yard but need no delivery. By hand, one person mixes about a cubic yard an hour, so the labor grows fast on bigger slabs.

How many bags of concrete do I need for a fence post?

For a 4 × 4 post set 3 ft deep in a 10 in hole, about 2 to 3 bags of 80 lb mix. The Post Hole Concrete Calculator works it out for any hole and post size and for several posts at once.

How do I calculate concrete for a sonotube or round pier?

Multiply π by the radius squared by the depth, all in feet. A 12 in tube 4 ft deep holds 3.14 cubic feet, or 6 bags of 80 lb mix. Choose Pier / Column in the calculator and enter the number of piers.

How thick should a concrete driveway be?

Most contractors pour residential driveways 4 inches thick for cars, and 5 to 6 inches where pickups, RVs or delivery trucks park. Some cities require more at the apron.

How much does a yard of concrete cost?

About $125 to $195 per cubic yard delivered in 2026, around $165 in much of the US, plus a short-load fee of $50 to $150 on small orders. In 80 lb bags, a yard costs $225 to $360.

How long does concrete take to cure?

Keep new concrete moist and above 50°F for at least 3 to 7 days. Its strength is specified at 28 days; at 7 days a typical mix has reached about 70% of it.

How much does a yard of concrete weigh?

About 3,780 to 4,050 lb, roughly two tons. Normal-weight concrete weighs 140 to 150 lb per cubic foot.

How much water do I add to an 80 lb bag of concrete?

Use the amount printed on the bag. Sakrete's High-Strength 80 lb mix, for example, calls for about 3.5 quarts. Adding more makes the mix easier to place but the concrete weaker.

Sources

  • ACI Committee 209. (1992). Prediction of creep, shrinkage, and temperature effects in concrete structures (ACI 209R-92). American Concrete Institute.
  • American Concrete Institute. (2012). Concrete craftsman series: Slabs-on-ground (CCS-1, 3rd ed.).
  • Forward Lift. (n.d.). Two post lift installation and owner's manual: Model I-10, capacity 10,000 lbs.
  • Headquarters, Department of the Army. (1998). Concrete and masonry (FM 5-428).
  • International Code Council. (2020). 2021 International Residential Code (Sections R311.3, R311.7.5, R402.2, R403.1.1, R506.1, R506.2.2, R506.2.3).
  • National Ready Mixed Concrete Association. (n.d.). SIP 3: Minimum cementitious materials content.
  • National Ready Mixed Concrete Association. (2016a). CIP 8: Discrepancies in yield.
  • National Ready Mixed Concrete Association. (2016b). CIP 36: Structural lightweight concrete.
  • National Ready Mixed Concrete Association. (2017). CIP 11: Curing in-place concrete.
  • National Ready Mixed Concrete Association. (2023). CIP 31: Ordering ready mixed concrete.
  • Pennsylvania Department of Transportation, LTAP. (2010). Estimating concrete amounts (Technical Information Sheet 143).
  • Quikrete. (n.d.). Concrete Mix No. 1101 [Product information].
  • Quikrete. (2022). Concrete Mix No. 1101 [Data sheet].
  • Sakrete. (2021). 5000 Plus Concrete Mix [Technical data sheet].
  • Sakrete. (2024). High-Strength Concrete Mix [Technical data sheet].

Updated .

Cite this page as:

Daniel, P. Concrete Calculator. Available at: https://constructioncalculators.com/concrete-calculator/. Accessed: October 28, 2026.