How Much Rip Rap Do I Need?
A bank 40 ft long and 10 ft along the slope, covered with Class I rip rap in a 12 in layer, takes 14.81 cubic yards, 25.93 tons. With 10% extra, order 28.52 tons.
Rip rap is sold and placed by the ton, and each class sets its own layer: picking a class in the calculator fills in its thickness. The extra covers uneven placement and the gaps you fill with smaller stone; the toe and end trenches are added area, covered below.
How to Measure a Slope for Rip Rap
Measure the width down the face of the slope, not across the ground. A bank that rises 5 ft over 10 ft of ground is 11.2 ft along the slope, so its rock covers 12% more area than the plan view suggests. In section:
- 1Filter fabric, or a stone filter at least 6 in thick
- 2Rip rap layer: 12 in for Class I
- 3Toe dug in below the foot of the bank
If you can't walk the slope with a tape, measure the height and the horizontal run and take the square root of the sum of their squares. HEC-23's revetment details also extend the rock beyond the slope itself:
- Top: at least 2 ft above the design high water, or to the top of the bank if the water reaches it.
- Toe: dug in below the foot of the bank, as deep as the bed may scour.
- Ends: keyed into the bank in trenches sized by the stone.
- Slope: no steeper than 1 vertical to 1.5 horizontal in its sketches; flatter slopes hold rock better.
Add the toe and the key trenches to the length and width you enter.
Rip Rap Classes and Sizes
The Federal Highway Administration's HEC-23 grades rip rap by the median stone, d50: half the stones by weight are larger. The layer comes from the stone size:
| Class | Median stone | Layer |
|---|---|---|
| I | 6 in | 12 in |
| II | 9 in | 18 in |
| III | 12 in | 24 in |
| IV | 15 in | 30 in |
| V | 18 in | 36 in |
| Class | Median stone | Largest stone | Median weight | Layer |
|---|---|---|---|---|
| I | 6 in | 12 in | 20 lb | 12 in |
| II | 9 in | 18 in | 60 lb | 18 in |
| III | 12 in | 24 in | 150 lb | 24 in |
| IV | 15 in | 30 in | 300 lb | 30 in |
| V | 18 in | 36 in | 1/4 ton | 36 in |
The median and largest stone of each class, to scale:
States use their own names, and the same number can mean very different stone:
| State | Class | Stone |
|---|---|---|
| North Carolina | Class A, Class B | 2–6 in, 5–12 in |
| North Carolina | Class 1, Class 2 | 5–17 in, 9–23 in |
| Pennsylvania | R-3, R-4 | 2–6 in, 3–12 in |
| Pennsylvania | R-5, R-6 | 4–18 in, 9–24 in |
| Virginia | Class AI, Class I | 25–75 lb, 50–150 lb |
| Virginia | Class II, Class III | 150–500 lb, 500–1,500 lb |
| Ohio | Type D, Type C | Mostly 3–12 in, 6–18 in |
| Ohio | Type B, Type A | Mostly 12–24 in, 18–30 in |
Penn State's dirt and gravel road center uses R-3 for road subbase, R-4 for ditches and R-5 and R-6 for streambanks. In or near a stream or a bridge, the permitting agency usually sets the class, and the stone is sized to the speed of the water.
How Thick Should Rip Rap Be?
At least 12 inches, and thicker as the stone gets bigger. The HEC-23 rules:
- Layer: at least the largest stone, at least 1.5 times the median stone and at least 12 inches, whichever is more (HEC-23). For every HEC-23 class, the largest stone governs: twice the median.
- Under water: 50% thicker.
- Filter: a geotextile, or a granular layer at least 6 inches thick or 4 times the median filter stone, under the rip rap.
- Light erosion control: Virginia DOT places its erosion control riprap, stones up to 15 inches, at least 8 inches thick.
Rip Rap per Square Foot
Each class needs a thicker layer, so the tons per square foot climb fast: 12 inches for Class I, then 6 inches more for each class up to 36 inches for Class V. Tons per 100 square feet of slope at those layers, with 10% extra:
Put the other way, a ton of rip rap covers about 15.4 square feet in a 12 inch layer and half that in a 24 inch layer.
How Much Does Rip Rap Weigh?
Tennessee DOT converts placed rip rap at 1.75 tons per cubic yard, which is what the calculator uses: about 3,500 lb per cubic yard, 130 lb per cubic foot or 2.1 metric tons per cubic meter. The Army's earthmoving manual gives 1.35 to 1.75 tons per loose yard for blasted rock. Solid rock weighs about 165 lb per cubic foot, so the gaps between stones take up about a fifth of a placed layer.
Rip Rap vs. Gabions, Walls and River Rock
Rip rap protects a slope that can stay a slope: stream and pond banks, ditches, culvert outlets and spillways. Where there is no room for a slope, a wall or gabions take over. Gabions are wire baskets filled with smaller stone, about 4 to 8 inches in Penn State's handbook; HEC-23 makes a gabion mattress at least twice as thick as its median fill stone. For a block wall that holds back soil, count the retaining wall blocks.
Surge stone and shot rock are looser terms with broader size ranges and no exact specification, so ask for a state class when it matters. Decorative river rock is too small and too round to hold a bank in moving water; it belongs in dry creek beds and gardens; calculate river rock for those. For the crushed stone filter layer under rip rap, get the crushed stone tons.
What Rip Rap Costs
Quarries sell rip rap for about $19 a ton for 6 in stone to $27 for 36 in stone, and $25 to $33 for 12 to 18 in stone; landscape yards charge about $60 to $127 a ton. At $60 a ton, rip rap costs about $3.89 per square foot in a 12 inch layer, $5.83 at 18 inches and $7.78 at 24 inches, before extra and delivery.
A large job takes several loads: the default 28.52 tons is two loads on a tandem truck, which carries roughly 13 to 18 tons, and each load may carry its own delivery charge. The default at $60 a ton plus $100 delivery comes to about $1,811.
Frequently Asked Questions
How much rip rap do I need?
Multiply the length by the width measured along the slope, in feet, and by the layer thickness in feet, divide by 27 for cubic yards and multiply by 1.75 tons per yard. A 40 × 10 ft bank with a 12 in layer takes 14.81 cubic yards, 25.93 tons; order 28.52 tons with 10% extra.
How much does a cubic yard of rip rap weigh?
About 1.75 tons, or 3,500 lb, the figure Tennessee DOT uses to convert placed rip rap from cubic yards to tons. That is about 130 lb per cubic foot, or 2.1 metric tons per cubic meter.
How thick should rip rap be?
At least the size of the largest stone, at least 1.5 times the median stone and at least 12 inches, whichever is more, by FHWA's HEC-23. Under water, add 50%. That makes 12 inches for Class I stone and 24 inches for Class III.
What size rip rap do I need?
It depends on how fast the water runs. Small ditches and slopes use 2 to 6 in stone, such as NCDOT Class A or Pennsylvania R-3 and R-4; streambanks use larger classes such as R-5 to R-7. For work near streams and bridges, the permitting agency or an engineer sets the class.
How big is Class 1 rip rap?
In FHWA's HEC-23 system, Class I has a 6 inch median stone and stones up to 12 inches, about 20 lb for the median stone. State classes differ: Virginia's Class I runs 50 to 150 lb per stone and North Carolina's Class 1 5 to 17 inches.
How big is Class 3 rip rap?
In HEC-23, Class III has a 12 inch median stone, stones up to 24 inches and a median weight of about 150 lb; it goes in a 24 inch layer. Virginia's Class III is much heavier, 500 to 1,500 lb per stone.
Do I need fabric under rip rap?
Yes, or a stone filter. HEC-23 puts a geotextile or a granular layer at least 6 inches thick, or 4 times the median size of the filter stone if that is more, under the rip rap so the soil does not wash out between the stones.
How much does rip rap cost?
Quarries sell rip rap for about $19 to $33 a ton, depending on size, and landscape yards for about $60 to $127 a ton. The default 28.52 tons at $60 a ton plus $100 delivery come to about $1,811.
How much does rip rap cost per square foot?
At $60 a ton, about $3.89 per square foot for a 12 inch layer of Class I, $5.83 for an 18 inch layer of Class II and $7.78 for a 24 inch layer of Class III, before extra and delivery.
Do I need a permit for rip rap?
Often, if it goes in or along a stream, lake or wetland. Check with your state's environmental or natural resources agency before you order the stone; the permit may also set the class and the layer.
Sources
- Headquarters, Department of the Army. (2000). Earthmoving operations (FM 5-434).
- Lagasse, P. F., Clopper, P. E., Pagán-Ortiz, J. E., Zevenbergen, L. W., Arneson, L. A., Schall, J. D., & Girard, L. G. (2009). Bridge scour and stream instability countermeasures (HEC-23, 3rd ed., Vol. 2; FHWA-NHI-09-112). Federal Highway Administration.
- North Carolina Department of Transportation. (2012). Standard specifications for roads and structures (Section 1042, Table 1042-1).
- Ohio Department of Transportation. (2013). Construction and material specifications (Section 703.19).
- Penn State Center for Dirt and Gravel Road Studies. (2025). Driving surface aggregate (DSA) handbook.
- Tennessee Department of Transportation. (n.d.). Structures calculation guide.
- Virginia Department of Transportation. (2020). Road and bridge specifications (Section 414).
Updated .
Cite this page as:
Daniel, P. Rip Rap Calculator. Available at: https://constructioncalculators.com/rip-rap-calculator/. Accessed: October 28, 2026.