How Much Does It Cost to Build a House?
A 2,142 square foot house, the median size of a new single-family house completed in 2025, costs about $367,503 to build at $171.57 a square foot, without the land. That is the 2025 median contract price per finished square foot for houses built by a general contractor on the owner's land.
The same house by region:
| Region | Per sq ft | 2,142 sq ft house |
|---|---|---|
| United States | $171.57 | $367,503 |
| Northeast | $179.30 | $384,061 |
| Midwest | $194.09 | $415,741 |
| South | $157.30 | $336,937 |
| West | $176.87 | $378,856 |
The national average was higher than the median, $198.33 a square foot, or $424,823 for the same house.
The median has been climbing: $163.15 a square foot in 2023, $165.15 in 2024 and $171.57 in 2025.
House Cost by Size
At the US median, and in the lowest- and highest-cost regions:
| House | US median | South | Midwest |
|---|---|---|---|
| 1,000 sq ft | $171,570 | $157,300 | $194,090 |
| 1,500 sq ft | $257,355 | $235,950 | $291,135 |
| 2,000 sq ft | $343,140 | $314,600 | $388,180 |
| 2,500 sq ft | $428,925 | $393,250 | $485,225 |
| 3,000 sq ft | $514,710 | $471,900 | $582,270 |
Real prices per square foot aren't flat: a small house still needs a kitchen, baths, a heating system and a foundation, so it tends to cost more per square foot than a large one.
Cost to Build a House per Square Meter
At the US median, $1,847 per finished square meter, and in the lowest- and highest-cost regions:
| House | US median | South | Midwest |
|---|---|---|---|
| 100 m² | $184,676 | $169,316 | $208,917 |
| 150 m² | $277,015 | $253,974 | $313,375 |
| 200 m² | $369,353 | $338,633 | $417,833 |
| 250 m² | $461,691 | $423,291 | $522,292 |
How to Calculate the Cost to Build a House
- 1Add up the finished floor area of every level you will heat and finish, from the plans. Leave out the garage, porches and any unfinished basement or attic.
- 2Choose your region; the price per square foot changes with it.
- 3Read the total and the split by stage, then add the land, site costs such as a well or septic system, and loan interest during the build.
What counts toward the finished square footage:
- 1Finished floors: counted
- 2Garage: not counted
- 3Porch: not counted
- 4Unfinished basement: not counted
- 5Unfinished attic: not counted
Where the Money Goes
Builders' costs split into stages:
| Stage | Share | 2,142 sq ft house |
|---|---|---|
| Site work, permits and fees | 7.6% | $27,930 |
| Foundation | 10.5% | $38,588 |
| Framing | 16.6% | $61,005 |
| Siding, roof, windows and doors | 13.4% | $49,245 |
| Plumbing, electrical and HVAC | 19.2% | $70,561 |
| Interior finishes | 24.1% | $88,568 |
| Driveway, landscaping and cleanup | 6.5% | $23,888 |
| Other | 2.1% | $7,718 |
Interior finishes and the three systems, plumbing, electrical and HVAC, are more than 40% of the cost. The structure itself, foundation and framing, is about a quarter. Use the stage lines to check a bid: price a slab or footings, and count the studs and plates.
What the Price Leaves Out
- Land: the contract price is for a house on land the owner already has.
- Site costs: a well, septic system, long driveway or utility runs to a rural lot.
- Financing: interest on the construction loan while the house is built. Work out the loan interest during the build and the payment after.
- Extras: a detached garage, pool or finished basement. Price a garage on its own.
Permits and Inspections During the Build
A new house needs a building permit before work starts (IRC Section R105.1), and the building official inspects it at set stages (R109.1): the footings and foundation before the concrete goes in, the plumbing, mechanical, gas and electrical rough-in before the walls are closed, the framing and masonry, and a final inspection. The house can't be occupied until the official issues a certificate of occupancy (R110.1). Each stage that fails inspection waits until it is fixed, so the schedule, and the interest on a construction loan, depend on passing them the first time.
Building a House Yourself
Acting as your own general contractor saves the builder's overhead and profit, but not the cost of the work. In new homes built for sale, construction itself was 64.4% of the sales price and the finished lot 13.7%; the builder's profit was 11.0%, overhead and general expenses 5.7%, and sales commissions, marketing and financing the rest.
An owner-builder still pays every trade and takes on the scheduling, the inspections and the cost of mistakes. Doing some of the work yourself, such as painting, trim or flooring, cuts the interior finishes line, the largest in the table above.
Build or Buy?
New houses built for sale by builders went for a median $154.79 a square foot in 2025, without the lot, against $171.57 for houses built under contract on the owner's land. A 2,142 sq ft spec house at that median comes to $331,560 before the lot.
Building costs more per square foot but buys the plan, the lot and the finishes you choose. Fixing up an existing house instead? Price the remodel by the square foot.
Frequently Asked Questions
How much does it cost to build a house?
About $367,503 for a 2,142 sq ft house at $171.57 a square foot, the 2025 median contract price for a new contractor-built house, without the land.
How much does it cost to build a house per square foot?
A median of $171.57 per finished square foot in 2025 for houses built by a general contractor on the owner's land, and an average of $198.33. The Midwest ran highest at $194.09 and the South lowest at $157.30.
How much does it cost to build a 2,000 sq ft house?
About $343,140 at the 2025 US median of $171.57 a square foot, from about $314,600 in the South to $388,180 in the Midwest, without the land.
How much does it cost to build a house on your own land?
The contract prices on this page are for exactly that case: a house built on land the owner already has. Add site costs the contract leaves out, such as a well, septic system or a long driveway, if your lot needs them.
Is it cheaper to build or buy a new house?
New houses built for sale went for a median $154.79 per square foot in 2025, not counting the lot, against $171.57 for houses built under contract on the owner's land. Building costs more per square foot but gets you your own plan on your own lot.
Does the price per square foot include the garage?
The square footage does not: it counts finished floor space only, without the garage, porch or unfinished basement. The contract price covers the whole house, so the garage is built into the price per square foot.
Does the cost include the land?
No. The contract price is for a house built on land the owner already has; add the lot, and any loan interest during the build, separately.
How much does it cost to build a house per square meter?
About $1,847 per finished square meter at the 2025 US median, so about $369,353 for 200 m², without the land. Switch the calculator to Metric to enter the area in m².
What inspections does a new house need?
Under the International Residential Code: the foundation before concrete is placed, the plumbing, mechanical, gas and electrical rough-in before they are covered, the frame and masonry, and a final inspection before the house is occupied. Local departments may add more.
What is the biggest cost in building a house?
Interior finishes, about 24% of construction cost: drywall, insulation, paint, flooring, cabinets, counters, trim and appliances. Plumbing, electrical and HVAC come next at about 19%, then framing at about 17%.
Sources
- International Code Council. (2020). 2021 International residential code (Sections R105.1, R109.1, R110.1).
Updated .
Cite this page as:
Daniel, P. House Construction Cost Calculator. Available at: https://constructioncalculators.com/house-construction-cost-calculator/. Accessed: October 28, 2026.